首页 | 本学科首页   官方微博 | 高级检索  
     检索      


Study on Compatibility between Converters and Casting Machines for Daily Steelmaking and Continuous Casting Scheduling
Authors:MA Feng-cai  ZHANG Qun
Institution:School of Economics and Management, University of Science and Technology Beijing, Beijing 100083, P. R. China
Abstract:In this paper, daily production scheduling is studied based on the Third Steelmaking Plant of Wuhan Iron and steel corporation (WISCO). To make sure the daily production plan is feasible, method of casting gToup is established, and the compatibility between two converters and three continuous casting devices in the Third Steelmaking Plant of WISCO is analyzed. The process flow chart of daily production scheduling is given in this paper. Then, algorithms and procedures for the simulation of daily production plan is developed. Using the actual data from the Third Steelmaking Plant, the feasible daily steelmaking plan and cast plan are given. The plan contains 7 groups of cast plan, figured out 54 converters, and a- bout 13,500 tons steel.
Keywords:Production Plan Simulation  Steelmaking  Continuous Cast
本文献已被 CNKI 维普 万方数据 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号