Abstract: | Although literature on the achievement of monetary objectives in a resource-constrained project environment is limited, the maximization of project net present value (NPV) is an important criterion of project success. This paper presents a procedure for developing a late-start resource-constrained project schedule using the critical path method-material requirements planning. Using an extensive set of problems from the literature, we show that this procedure yields a higher NPV and lower average duration than schedules derived with heuristics that schedule each activity as early as possible. In addition, while the late-start schedule on average was significantly longer than the optimal-duration resource-constrained schedule, no significant difference occurred in the average NPVs of the two scheduling methods. |