考虑作业空间干涉的工程项目时间-成本均衡优化研究
引用本文:李迁,陶莎,周晓园,盛昭瀚. 考虑作业空间干涉的工程项目时间-成本均衡优化研究[J]. 中国管理科学, 2019, 27(10): 170-178. DOI: 10.16381/j.cnki.issn1003-207x.2019.10.017
作者姓名:李迁  陶莎  周晓园  盛昭瀚
作者单位:南京大学工程管理学院, 江苏 南京 210093
基金项目:国家社会科学基金重大资助项目(18ZDA043);国家自然科学基金资助项目(71571098,91646123,71671088,71501102,71471077)
摘    要:工程现场的空间资源是制约工程活动开展的重要影响因素。本文研究考虑空间干涉的工程调度优化问题,定义作业空间干涉的度量方式和作业效率函数,建立工程调度的工期-成本双目标优化模型。针对问题特征设计相对延迟编码方式和解码机制,采用NSGA-II算法求解模型。以某工程案例为研究对象,通过与传统方法对比实验验证了模型和算法的有效性,接着分析了算法的最大延迟时间参数对算法性能的影响。实验结果表明,本文提出的模型和算法能有效提升工程进度和成本目标。

关 键 词:工程调度  作业空间干涉  作业效率  工期-成本优化  NSGA-II  
收稿时间:2018-10-09
修稿时间:2019-04-12

Time-Cost Trade-off Optimization of Construction Project Considering Workspace Interference
LI Qian,TAO Sha,ZHOU Xiao-yuan,SHENG Zhao-han. Time-Cost Trade-off Optimization of Construction Project Considering Workspace Interference[J]. Chinese Journal of Management Science, 2019, 27(10): 170-178. DOI: 10.16381/j.cnki.issn1003-207x.2019.10.017
Authors:LI Qian  TAO Sha  ZHOU Xiao-yuan  SHENG Zhao-han
Affiliation:School of Engineering and Management, Nanjing University, Nanjing 210093, China
Abstract:Except for labor, equipment, materials resources, space is an important resource for construction activity execution. Space resource required by construction activity means the occupation of two-dimensional or three-dimensional space in construction site during the execution of construction activity. Since the construction site is often fixed and space is limited, space interferences among activities often happen in construction practice, which would reduce productivity, lead to construction delay and cost overrun. Therefore, more and more researchers in construction management field have paid great attention on space interference. When scheduling a construction project, construction project manager should try to prevent or mitigate space interference among activities, which is of great significance to construction practices.Previous studies have indicated that space interference can decrease resource productivity which leads to a longer actual duration than expected. Therefore, the influence of space interference on productivity is taken into account in this paper. The construction scheduling problem with variable duration under the influence of space interference is studied. The problem is to optimize two goals simultaneously:project makespan and total cost. To be more specific, the degree of space interference is measured and the productivity function of space interference is proposed. Then, a bi-objective programming model is established. The solution of the model conclude two parts:1) the execution time of each activity; 2) mode selection for each activity. In terms of execution time, the model should determine not only the start time but also the actual duration for each activity, since the actual duration is variable in this problem. In order to solve the problem efficiently, the NSGA-II is adopted where a specific encoding method based on relative delay time and the corresponding decoding mechanism are designed. Finally, the model and the algorithm are verified by analyzing a construction project case. By comparing with the traditional scheduling method, the experimental results show that NSGA-II can reduce the space interference more effectively and improve both two objectives. For the construction case used here, the Pareto solutions saves 3.09% on project makespan and 1.01% on total cost when mode selection being fixed. Comparison experiments are also conducted to explore the influence of critical parameter——maximal relative delay time on the performance of NSGA-II. The experimental results indicate that when the maximal relative delay time be set as 40, the NSGA-II has the best performance on solving the case.This research has a certain practical guidance for construction management in reality. It can provide a scientific and reasonable decision support for project managers. It also enriches the theoretical study in the field of construction management and resource-constrained project scheduling problem.
Keywords:construction scheduling  workspace interference  productivity  time-cost optimization  NSGA-II  