郑新黄河大桥主桥钢桁梁跨河架设方案研究
引用本文:孟庆贺.郑新黄河大桥主桥钢桁梁跨河架设方案研究[J].石家庄铁道学院学报(社会科学版),2009(4):56.
作者姓名:孟庆贺
作者单位:河南中原高速公路股份有限公司 中原大桥分公司
摘    要:郑新黄河大桥主桥第一联,为跨越黄河天险而设计成六塔单索面部分斜拉连续钢桁结合梁。本桥可采用跨线龙门吊机悬臂架设方案,亦可采用回转架梁吊机悬臂架设方案,也可采用整体顶推架设方案。就三种架设方案进行了详细的比选,最终优选出多点同步连续顶推方案为本桥的架设方案。

关 键 词:公铁两用桥  钢桁梁  悬臂架设  顶推架设
收稿时间:2009/10/12 0:00:00

Research of Erection Schemes for Steel Truss Girders of Main Bridge
Authors:Meng Qinghe
Institution:Zhongyuan Bridge Branch of Henan Zhongyuan Expressway Co., Ltd
Abstract:The first unit of Zhengzhou Yellow River rail cum road bridge is a six pylon and single cable plane cable stayed continuous steel truss girder bridge. The schemes for the erection include cantilever erection with gantry crane or girder erection crane, and pushing for installation. Through comparison and research of different erection schemes, it is determined that the first unit of the girder is to be erected by the multi point longitudinal hauling scheme.
Keywords:rail cum road bridge  steel truss girder  cantilever erection  pushing for installation